Annual Paving Program

2026 Paving Program


Overview

In 2015 Tetra Tech EBA and Urban Systems conducted a pavement condition assessment of the City's road network and developed the existing Pavement Management Plan (2017). In 2020, Tetra Tech completed a second roadway pavement condition assessment and updated the City's Pavement Management System. The resources are used to identify capital utility and paving projects, and annual maintenance work plans.


2026 PAVING LOCATIONS

  • Nichol Road (Park Drive to Road About)
  • Third Street East, Northbound Lane (Mackenzie Avenue to Victoria Road)
  • Third Street East, Southbound Lane (Mackenzie Avenue to Orton Avenue)
  • Third Street West (Charles Street to Ford Street)
  • Mackenzie Avenue ( Eighth Street East to Ninth Street East )
  • Airport Way, Southbound Lane (Newland Road to Nichol Road)
  • Park Drive (Arrow Drive to McKinnon Road)
  • Big Eddy Road (Celgar Road to Begbie Road)
  • First Street West (Charles Street to King Street)
  • Peterson Drive (Laforme Boulevard - 1984 Fairway Road


CONSTRUCTION IMPACT

Sections of road will require closures throughout the construction period. Notices will be delivered to impacted residents a minimum of 48 hours prior to planned shutdowns or road closures. Expect equipment noise and increased numbers of construction vehicles. Road closures and detours will be clearly marked with traffic cones, and traffic control persons when required. Please follow all detour routes, drive cautiously, and protect our construction workers.


TIMELINE

Paving will be completed by October 31st, 2026.