Annual Paving Program
2025 Paving Program
Latest Status
At the July 22nd Council Meeting, the City awarded the 2025 Asphalt Resurfacing Service Project to Terus Construction Ltd.
Overview
In 2015 Tetra Tech EBA and Urban Systems conducted a pavement condition assessment of the City's road network and developed the existing Pavement Management Plan (2017). In 2020, Tetra Tech completed a second roadway pavement condition assessment and updated the City's Pavement Management System. The resources are used to identify capital utility and paving projects, and annual maintenance work plans.
2025 PAVING LOCATIONS
- 3rd St W, from King St to Wright St
- Wright St, from Douglas St to Front St
- Front St, from Wilson St to End
- 8th St E, from Victoria Rd to Temple St
- Campbell Ave (eastbound), from turning lane to 4th St E
- Campbell Ave (westbound), from 1st St W to 3rd St W
- 8th St E, from Downie St to Edward St
CONSTRUCTION IMPACT
Sections of road will require closures throughout the construction period. Notices will be delivered to impacted residents a minimum of 48 hours prior to planned shutdowns or road closures. Expect equipment noise and increased numbers of construction vehicles. Road closures and detours will be clearly marked with traffic cones, and traffic control persons when required. Please follow all detour routes, drive cautiously, and protect our cone zone workers.
TIMELINE
Paving will be completed by October 31st, 2025.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends